Summary
The matter of the case is an out-of-court dispute resolution between two industrial companies on the enforcement of a foreign court decision. Adoption of precautionary measures. There is a new conflict between the parties concerning the costs of the proceedings. Court decision: no costs of the proceedings must be imposed derived from the execution. The enforcement of the foreign court decision is not a final judgment (one of the parties appealed the enforcement according to arts. 38 and 43 of Brussels I Regulation). The court admits the imposition of precautionary measures in accordance with Brussels I Regulation (art. 47.2) and CJEU case law. Appeal history (not available in the database): Court decision: Juzgado de Primera Instancia Nº 1 de Aranda de Duero (Burgos) (Spain) (First instance) Date: 02-11-2004

This website is written and maintained by the University of Aberdeen's Research Applications and Data Management Team