PIL instrument(s)
Brussels I
Case number and/or case name
Unico International Development S.L.Roj: AAP M 809/2013 - ECLI:ES:APM:2013:809A
Details of the court
Spain, Second Instance
Articles referred to by the court
Brussels I
Article 2
Paragraph 1
Paragraph 2
Article 3
Paragraph 1
Date of the judgement
17 January 2013
Appeal history
None
CJEU's case law cited by the court
None
Summary
Conflict of jurisdiction based on the application of Brussels I Regulation provisions. Key facts: Commercial matters case. The matter of the case is a dispute on the validity of an agreement on jurisdiction to Moroccan courts. between parties. The defendant is a company domiciled in Spain. A first instance Spanish court decided that Spain was not competent to decide on the case. Court decision: Spanish courts are competent to decide on the case according to arts. 2 and 3.1 of Brussels I Regulation (defendant´s domicile in Spain). The court applies Brussels I Regulation general provisions on jurisdiction, which points to the Member State courts where the person sued is domiciled. Appeal history (not available in the database): Court decision: Juzgado de Primera Instancia nº 82 de Madrid (Spain) (First instance) Date: 04-07-2012

This website is written and maintained by the University of Aberdeen's Research Applications and Data Management Team